# The plan from here: Paperclip underneath, a Go terminal app on top
|
||||
|
||||
Written 2026-11-09. Read with `WHAT-WE-ARE-BUILDING.md`. This is the third attempt, and
|
||||
it says where we have been as well as where we are going, because the first two were
|
||||
lost by plans that only said "next".
|
||||
|
||||
---
|
||||
|
||||
## 1. What we set out to make
|
||||
|
||||
A coding factory that runs inside TUIOS. A person writes a goal; it is split into tasks;
|
||||
each task runs on its own copy of the code; tests and a review decide whether the work is
|
||||
finished; finished work is merged one at a time; the person is interrupted only to make a
|
||||
decision. Terminal only. Per project, not per machine.
|
||||
|
||||
## 2. Where we have been
|
||||
|
||||
**Attempt one (OMA, our own cockpit).** We built a coordinator around the
|
||||
`@open-multi-agent` library, which is genuinely good at planning a task graph and
|
||||
verifying output. Then we spent two weeks building the things it does not have: an
|
||||
approval path, a viewer, a task starter, a card board. Those were built twice, because
|
||||
faults appeared in threes — two implementations of the same job disagreeing.
|
||||
|
||||
**What went wrong, specifically.**
|
||||
|
||||
- Nothing was ever run end to end on a small plan. Every failure had several causes, so
|
||||
every fix was a guess.
|
||||
- The interface came before the engine: nine pages, panes, notes and filters before one
|
||||
task had passed one test.
|
||||
- A plan that was re-run was re-planned, which silently threw away its dependencies.
|
||||
- A task's state was guessed from folder names, so old work coloured new cards.
|
||||
- The layout was lost twice: TUIOS deletes a workspace when its last pane closes, and a
|
||||
repair command did not carry the project with it.
|
||||
|
||||
**What we achieved and keep.** A working page layout and page notes in plain language; a
|
||||
project convention (`.harness/settings.toml`, role files, notes, a to-do list per
|
||||
project); `office` for opening a project; `project-reset`; and a real understanding of
|
||||
what an approval and a per-task check must be (`plan/90`).
|
||||
|
||||
**Attempt two (understanding, not building).** We read OMA properly and found it has
|
||||
approvals, checks and worktrees of its own kind. We then studied Paperclip instead of
|
||||
assuming.
|
||||
|
||||
## 3. What Paperclip actually is, from our own probes
|
||||
|
||||
Not marketing — measured on this machine (`spike/api-notes.md`).
|
||||
|
||||
- A server with a database, already running here: `http://127.0.0.1:3100`, 685 API
|
||||
endpoints, browser UI at `https://paperclip.lab.audasmedia.com.au`.
|
||||
- Your work is already in it: 10 projects, 145 tasks, with statuses `todo`, `backlog`,
|
||||
`in_progress`, `blocked`, `done`.
|
||||
- **Pi is the worker already installed** on the agent identity (`adapterType: pi_local`).
|
||||
- Blockers are real: setting one returned "1 unresolved blocker" and named the task that
|
||||
blocks it. **But the blocker is not on the task list**, only on the single task and its
|
||||
blocker diagnosis. A tree must ask per task.
|
||||
- Comments land on a blocked task's thread.
|
||||
- **Cost per task is readable** — cents, input and output tokens, run count.
|
||||
- **Writes from an agent key are refused** unless it is inside a heartbeat run. A person's
|
||||
tool must use the user key. This is Paperclip protecting its own audit trail.
|
||||
- **Paperclip creates git worktrees itself.** The installed code runs `git worktree` and
|
||||
enforces a workspace strategy of `git_worktree` with a branch template, a worktree
|
||||
parent folder, and setup and teardown commands. The worktree was on our list; it is
|
||||
not ours to build.
|
||||
|
||||
## 4. Pitfalls, so the third attempt does not repeat the first two
|
||||
|
||||
1. **One owner per fact.** The task queue, blockers, approvals, comments, runs and cost
|
||||
belong to Paperclip. Our code never keeps a second copy. If a screen disagrees with
|
||||
Paperclip, the screen is wrong.
|
||||
2. **No interface before a working run.** The first milestone ends with a task that a
|
||||
person watched finish. Nothing is styled before that.
|
||||
3. **Small plans only, until small plans work.** Two tasks, then three, then a real job.
|
||||
4. **Never judge a task by a folder name.** State comes from the task's record.
|
||||
5. **The layout is ours to protect.** A workspace dies when its last pane closes, so
|
||||
every page keeps a pane that does not close. Repair must carry the project name.
|
||||
6. **Agent keys are not person keys.** Anything the TUI does on your behalf uses the user
|
||||
credential, so the audit trail names you.
|
||||
7. **Do not re-plan a plan.** A stored plan is read, never regenerated.
|
||||
8. **Every claim comes with the command that showed it.**
|
||||
|
||||
## 5. What Paperclip does not do, and is ours
|
||||
|
||||
- **Per project, not per company.** Paperclip has companies, projects and tasks. Our unit
|
||||
of work is one project in one folder on one machine. Mapping and scoping are ours.
|
||||
- **Which host.** Moving between `.13`, `.27` and `.51`, remembering where a project
|
||||
lives and building its layout there. Ours.
|
||||
- **The layout and its repair.** Pages, panes, and rebuilding them after a crash or on a
|
||||
new machine. Ours.
|
||||
- **Project lifecycle.** Create, adopt, reset, delete. Ours.
|
||||
- **The code review gate.** `ocr` over the diff, and the merge order. Paperclip has
|
||||
approvals; it does not know our review tool.
|
||||
- **Serial merging.** One task at a time, re-checked after each rebase. Ours.
|
||||
- **The wording of a task's test.** Paperclip records a task; the command that decides it
|
||||
is finished is our convention, kept with the project.
|
||||
- **The notes.** What each screen is for, in plain language. Ours.
|
||||
|
||||
## 6. The shape: four screens, one Go program
|
||||
|
||||
Go, with Bubble Tea, Lipgloss, Bubbles, Huh and BubbleZone. One program, four screens,
|
||||
each in a TUIOS pane. All data comes from Paperclip's API; nothing is stored twice.
|
||||
|
||||
**Screen 1 — Task tree.** Todo, in progress, blocked, done, for the current project. Each
|
||||
row shows the task, who has it, and what blocks it (read per task, not from the list).
|
||||
Enter opens the task. This replaces the old HOME, BOARD and DONE pages.
|
||||
|
||||
**Screen 2 — New task.** A form: title, description, what must finish first, and the test
|
||||
that decides it is done. On submit it calls Paperclip, and the task appears in the tree.
|
||||
|
||||
**Screen 3 — Live log and diff.** For the selected task: what the agent is doing, the
|
||||
files it touched, and the change as a diff. Reads Paperclip's run and activity records;
|
||||
the diff comes from the task's own worktree, which Paperclip made.
|
||||
|
||||
**Screen 4 — Unblock and reply.** The task's thread, with a box to reply. Sending posts a
|
||||
comment, and optionally changes status — which is what wakes the agent.
|
||||
|
||||
Around those four, the things we already know we need, kept as thin pages rather than a
|
||||
second application: project open/reset, the notes page, and a repairs page that rebuilds
|
||||
the layout.
|
||||
|
||||
## 7. Plan of attack
|
||||
|
||||
**Milestone 0 — done.** Read-only probe of the API, plus sandbox writes. Results in
|
||||
`spike/api-notes.md`.
|
||||
|
||||
**Milestone 1 — one task, really run.** In the sandbox project, give the task to Pi,
|
||||
let Paperclip make the worktree and run it, and see the comment and the status change
|
||||
come back. Pass when: the task goes todo → in progress → done, a comment written by Pi
|
||||
holds the change, and the cost appears. No interface.
|
||||
|
||||
**Milestone 2 — screen 1 and screen 4.** Read the tree from the API, and reply from a box.
|
||||
Pass when: you move a blocked task forward entirely from the terminal, without a browser
|
||||
and without a shell command.
|
||||
|
||||
**Milestone 3 — screen 2 and screen 3.** Create a task with a blocker and a test; watch a
|
||||
running task's log and diff. Pass when: a two-task plan is created, ordered and finished
|
||||
from the terminal alone.
|
||||
|
||||
**Milestone 4 — the project layer.** Adopt a folder, remember its host, build the layout,
|
||||
repair it, reset it. Pass when: a new project on another machine can be opened and used
|
||||
from here.
|
||||
|
||||
**Milestone 5 — the review gate and merging.** `ocr` over the diff, and serial merge.
|
||||
Pass when: a task that fails review is refused, and the next task cannot merge until the
|
||||
first is settled.
|
||||
|
||||
## 8. On the Bubble Tea analysis
|
||||
|
||||
It is correct, and it names the two things that would otherwise cost a week:
|
||||
|
||||
- **Resize.** Handle the window-size message, never hardcode sizes, subtract border
|
||||
sizes, and show a short "too small" screen rather than a broken one. Also run in the
|
||||
alternate screen so TUIOS scrollback does not fight the redraws.
|
||||
- **Keys.** In TUIOS window mode, `h j k l`, `z` and `n` belong to TUIOS and never reach
|
||||
the app. So inner navigation uses Tab, Shift-Tab, arrows, Space and Enter, and a bare
|
||||
Esc must be free to close a box. This is a design constraint, not a detail.
|
||||
|
||||
Two additions from our own experience:
|
||||
|
||||
- Wrap the whole top-level view in one BubbleZone scan, and create the zone manager once.
|
||||
Per-component scanning drifts when panes resize.
|
||||
- Never do network or git work inside the update or view functions; do it in commands
|
||||
that return messages. A freeze is visible to the person as a stuck pane.
|
||||
|
||||
## 9. Decisions this plan needs from the person
|
||||
|
||||
1. Confirm Paperclip as the owner of tasks, blockers, comments, approvals, runs and cost.
|
||||
2. Confirm the four screens and the thin pages around them.
|
||||
3. Confirm that the first milestone runs a task with no interface at all, even though the
|
||||
interface is the part you most want to see.
|
||||